DESIGN INTENT / COORDINATION -- not IFC, not a bar-bending schedule, not a contractor quote. Iron (saria) by diameter and tonnes, RMC M25 by element and mixer trips (rate not quoted), AAC 8 in / 6 in / 4 in boundary, cement bricks for plinth stem only. Rates are Rajesh expected/approx 29 Aug 2026. Stair is a dog-leg (straight waist), not curved; steel already counted as four flights. Member sizes are an SE hold. Do not invent SBC.

Soil report outstanding -- footings and founding are placeholders

No geotechnical report has been received. Isolated footings 5-0 x 5-0 x 1-6 and a 4-6 founding depth are COORDINATION only. Do not invent SBC. Reissue before excavation. Column 230 x 450 mm on this sheet is a takeoff assumption; C-01 still reads 230 x 600 mm. Both are PROVISIONAL pending the structural engineer to IS 13920 (Seismic Zone IV).

Drawing hold -- AAC thickness / boundary

Drawings tag EXT 200 mm AAC / INT 100 mm Zmart AAC. This takeoff uses 8 in (200 mm) external (now matching the drawings), 6 in (150 mm) internal (drawings still 100 mm), and 4 in AAC x 6-0 for the plot boundary. Superstructure is AAC, not clay. RCC bricks are plinth stem only -- not compound backing. South F2C and the two large north lights are deducted. South compound stone face is a finish, not this sheet.

Headline totals (with wastage) -- DESIGN INTENT

Steel Fe 500D 24.06 t (itemised 22.91 t). RMC M25 206.9 m3 (35 x 6 m3 mixers, rate not quoted). AAC 8 in 2,747. AAC 6 in 3,941. AAC 4 in boundary 938. Cement bricks 26,781 nos (51.0 m3, plinth stem). Expected raw-material subtotal ₹22,87,694.50 (no GST / labour / RMC / finishes). Not IFC.

Project PLOT 208B Residence · GMADA New Chandigarh Plot 50'-0" × 90'-0" · 500 sq yd Prepared by Stellar · issued for coordination Discipline ARCHITECTURAL Structure & foundation · takeoff Drawing MATERIALS -- STEEL & RMC Rev F/G · 29 Aug 2026 Sheet C-10 N.T.S. at A3 A3 landscape Status DESIGN INTENT COORDINATION Not for construction. Member sizes provisional pending SE. Not IFC. DESIGN INTENT · COORDINATION · NOT IFC · NOT BBS208B · Civil materials -- structure & foundation · Rev F/G · Fe 500D · RMC M25 · Seismic Zone IVLocked geometry A 4-4 B 16-0 C 29-6 D 44-8 / 1 12-0 2 29-9 3 47-6 4 58-6 5 75-0 · Palatino italic on the drawings.Member sizes PROVISIONAL pending SE and soil report. Typical residential Zone IV intent -- not a BBS.STEEL +5%24.06 tFe 500D TMTRMC M25 +3%206.9 m335 x 6 m3 mixersAAC 8 in +5%2,747 nos625x250x200 mmAAC 6 in +5%3,941 nos625x250x150 mmAAC 4 in BND938 nos6-0 high, assumed rateRAW MAT. SUB₹22,87,694.50RMC / GST / labour outSTEEL BY MEMBER · Fe 500D TMT · IS 1786 · DESIGN INTENTMember (INTENT, not BBS)8 mm kg10 mm12 mm16 mm20 mmkgtColumns 20 house719--659308544634.46Porch pillars 268--632944250.43Footings bottom mesh 12 both ways @150--784--7840.78Plinth beams 4-16 long---961-9610.96Plinth beams 2-12 long--270--2700.27Plinth stirrups 8 @150328----3280.33F/R beams 3-20 (17'-9" spans)----387038703.87F/R beams 2-16 top---1653-16531.65F/R beams 1-12 hanger/extra--465--4650.46F/R stirrups 8 @100/1501803----18031.80Slabs 10 both ways @150 bottom-5802---58025.80Slabs 8 extra top ~40% both ways1486----14861.49Lintels 2-12--135--1350.13Lintels 2-10-94---940.09Lintels 8 stirrups133----1330.13Stair waist 12 main--70--700.07Stair waist 8 dist35----350.03Sump 12 (small)--71--710.07Sump 816----160.02Kerb 10-52---520.05TOTAL ITEMISED458859471795333672492291422.91+ 5% wastage-----2406024.06STEEL BY DIAMETER · order TMT Fe 500D · +5% wastage on the last columnsDiaUnit wtRunning mRunning ftkg itemt itemkg +5%t +5%8 mm0.395 kg/m11614 m38105 rft4588 kg4.59 t4817 kg4.82 t10 mm0.617 kg/m9638 m31622 rft5947 kg5.95 t6244 kg6.24 t12 mm0.888 kg/m2021 m6630 rft1795 kg1.79 t1884 kg1.88 t16 mm1.580 kg/m2111 m6927 rft3336 kg3.34 t3503 kg3.50 t20 mm2.466 kg/m2940 m9645 rft7249 kg7.25 t7612 kg7.61 tALL DIA-28325 m92928 rft2291422.912406024.06BAR INTENT BY ELEMENT · sizes named · not a cutting length / BBSElementMain barsLinks / dist.Takeoff noteColumns / porch pillars6-20 mm + 2-16 mm main8 mm stirrups @ 150 / 100 c/c230x450 takeoff (C-01 says 230x600)Plinth / grade beams4-16 mm + 2-12 mm8 mm stirrups @ 150230x300 on locked gridFloor / roof beams3-20 + 2-16 + 1-128 mm @ 100 near support / 150 mid230x450 · longest span 17-9Slabs 125 mm10 mm @ 150 both ways bot.8 mm extra top ~40%GF/FF minus atrium · roof minus skylightFootings12 mm both ways @ 150bottom mesh, 50 mm cover5-0 x 5-0 x 1-6 INDICATIVELintels2-12 mm + 2-10 mm8 mm stirrups @ 150230x150 · not F2C / N lightsRMC BY ELEMENT (grouped) · M25 ALL structural RCC · Zone IV · full list in CSVElementGradeMethodm3+3% m3Footings 20 house + 2 porchM255-0 x 5-0 x 1-6 INDICATIVE23.3624.06Columns 20 + porch pillars 2M25230x450 · C-01 drawing says 230x60021.4922.13Plinth beams 230x300 on gridM25locked 4 x 5, atrium ring kept9.549.83Floor/roof beams 230x450M253 levels + porch/balcony edge49.2250.70Slabs 125 mm GF+FF+roof+mumtyM25minus atrium / skylight88.1590.80Stair + lintels + kerb + sumpM25west well, 50 lintels, 6000 L9.139.41TOTAL M25 RMCM25ALL structural -- NOT M20 columns200.90206.92Order 35 mixers x 6 m3M25Chandigarh transit +3% wastage-206.92Cross-check: 22914 kg itemised / 200.90 m3 RCC = 114 kg/m3 (band 80-100; Zone IV + 17-9 sits high). PCC M10 is SITE-MIX, not RMC.
C-10 · Steel by member and diameter · RMC M25 by element · DESIGN INTENT
Project PLOT 208B Residence · GMADA New Chandigarh Plot 50'-0" × 90'-0" · 500 sq yd Prepared by Stellar · issued for coordination Discipline ARCHITECTURAL AAC 8 / 6 / 4 · plinth bricks · PCC · cost Drawing MATERIALS -- MASONRY & FOUNDATION Rev F/G · 29 Aug 2026 Sheet C-11 N.T.S. at A3 A3 landscape Status DESIGN INTENT COORDINATION Not for construction. Member sizes provisional pending SE. Not IFC. DESIGN INTENT · COORDINATION · NOT IFC · NOT BBSUSER sizes: AAC 8 in (200 mm) EXT / AAC 6 in INT / AAC 4 in boundary x 6-0. Drawings already 200 mm EXT; INT drawings still 100 mm Zmart -- HOLD. Superstructure is AAC, not clay. RCC bricks = plinth stem only.AAC 8 INCH · EXTERNAL WALLS · USER SIZE (drawings already 200 mm) · 625 x 250 x 200 mmAAC 8 in (200 mm) EXTERNALBasism2BlocksGF external (envelope - openings)207 ft x 11-0 - F2C/windows/doors161.3 m2-FF external (house + balcony-facing)185 ft x 11-0 - N lights / E-W modules135.5 m2-Roof parapet +9915terrace perimeter x 1.70 m (M2 field)107.8 m2-Mumty walls +12015stair well 11-8 x 11-0 x 2.10 m - door27.2 m2-NET AREA / BLOCKS 625x250x200face 0.1651 m2/block (10 mm joint) t=8 in431.8 m22615+ 5% wastage · ORDERcommon Indian AAC 625x250x200 mm-2747AAC 6 INCH · INTERNAL WALLS · USER SIZE · 625 x 250 x 150 mmAAC 6 in (150 mm) INTERNALBasism2BlocksGF internal partitions376 ft x 11-0 - 8-0 door leaves357.0 m2-FF internal partitions278 ft x 11-0 - 8-0 door leaves262.6 m2-NET AREA / BLOCKS 625x250x150same face module, 150 mm thick619.5 m23752+ 5% wastage · ORDERcommon Indian AAC 625x250x150 mm-3941AAC 4 INCH · COMPOUND 6-0 HIGH · NOT CEMENT-BRICK BACKING · 625 x 250 x 100 mmAAC 4 in BOUNDARY / COMPOUNDBasism2BlocksPlot perimeter minus SW gate2x(50+90) - 12-0 veh - 3-6 ped = 264.5 ft--Height 6-0 · thickness 4 inface 0.1651 m2/block t=102 mm147.4 m2893+ 5% wastage · ORDER625x250x100 mm · rate ASSUMED pro-rata, not quoted-938Stone face (south)finish only -- not this purchase sheet--FOUNDATION STEM · PLINTH INFILL ONLY · 230 x 110 x 75 mm · NOT COMPOUNDRCC / cement bricks (plinth stem only)Basism3NosPlinth / stem under wallsfooting top to plinth soffit 1.41 m x 8 in x GF wall lines51.01 m3-Compound backingNONE -- boundary is 4 in AAC x 6-0 (above)--TOTAL / +5% ORDERsolid cement brick 230x110x75, plinth stem ONLY51.01 m326781EXPECTED RAW MATERIAL COST · NOT A CONTRACTOR QUOTE · RMC NOT QUOTED · 4 in RATE ASSUMEDExpected raw material (29 Aug 2026, Rajesh)Qty with wastageRate INRAmountIron Fe 500D TMT24.06 t₹55,000 / t₹13,23,300Cement 50 kg (site-mix only)232 bags₹400 / bag₹92,800RCC / cement bricks26781 nos₹9.50 / brick₹2,54,419.50AAC 8 inch2747 nos₹100 / block₹2,74,700AAC 6 inch3941 nos₹75 / block₹2,95,575AAC 4 inch boundary [ASSUMED]938 nos₹50 / block (assumed)₹46,900SUBTOTAL these six linesRMC / GST / labour / cartage / finishes outexpected/approx₹22,87,694.50OTHER · PCC · DPC · SHUTTERING · UNPRICED LINES (rate not quoted)Other -- structure & foundationSpecBasisQtyPCC blinding under footingsM10 1:4:8 site-mix22 x 1.824x1.824x0.1027.44 m3PCC under plinth stripsM10 1:4:8 site-mix0.45 m wide x 4 in x wall lines8.12 m3Sand filling in plinth150 mm over earth fill221 m2 x 0.1533.2 m3DPC + waterproofing40 mm M20 site-mixon EXT 8 in + INT 6 in wall lines1.20 m3Shuttering ply + battensRENTAL, rate not quotedfoot+col+beam 3-side+slab soffit1711 m2Cover / chairs / wirerate not quoted6713 + 2820 nos + 241 kg-Anti-termite (foundation)IS 6313, rate not quotedtrench bottoms+sides + plinth369 m2Cement site-mix 50 kg bagsPCC+DPC+mortar; NOT structural RMCceil(x1.03) priced above232 bagsMortar 1:6 AAC / 1:4 brick8+6+4 AAC; brick = stem only19.56 / 11.22 m3-RMC M25rate not quoted -- do not invent Rs/m3200.90 m3 +3% = 206.9235 mixersASSUMPTIONS · DESIGN INTENTGrid locked. Envelope 41 x 63. 19 free columns + A5 flush in west wall.Footings 5-0 x 5-0 x 1-6 INDICATIVE. Founding 4-6 is a placeholder -- no SBC invented.Columns 230x450 takeoff (C-01 230x600). RMC M25 all structural. PCC M10 site-mix.AAC 625x250xt, 10 mm 1:6. Storey 11-0. Parapet 1.70 m. Boundary 4 in x 6-0.Wastage steel 5%, RMC 3%, AAC 5%, bricks 5%. Cement buy = ceil(bags x 1.03).West parking open sky. No transfer girder. Kankar / OHT / finishes not this sheet.SE HOLDS · NOT FOR CONSTRUCTIONSoil report outstanding. Do not invent SBC. Reissue footings before excavation.INT walls: drawings 100 mm vs takeoff 6 in. Columns 230x600 vs 230x450.Rates expected/approx 29 Aug 2026 Rajesh. No GST, cartage, labour, RMC, finishes.4 in AAC Rs 50 is ASSUMED pro-rata (6 in/8 in both ~Rs 12.50/inch). Not quoted.Cement inside RMC is not a second buy. This is not a BBS, IFC, or contractor quote.Script: plot-208b-rev-c/_materials_takeoff.py · workings.txt sits beside it.
C-11 · AAC 8 in / 6 in / 4 in boundary · plinth bricks · expected raw-material cost